A weekly A–F grade for new large-load interconnection in ERCOT, SPP, MISO, PJM, and WECC. Open a market for the current grade and the series behind it. Published since July 16, 2026.
Power availability · updated weekly
As of October 26, 2026
Schematic. Regions approximated to state lines; outlined states are not graded.
Texas
Electric Reliability Council of Texas
A-Trending down
TCEQ letter Oct 19; STEERS down. Freeze still binds to Dec 10.
Central United States
Southwest Power Pool
B+Holding
ER26-3685 still no FERC order. CHILL path still open.
Midwest and South
Midcontinent Independent System Operator
CHolding
ER26-3650 still no FERC order. Dec 4 requested. Process, not reserve margin.
Mid-Atlantic and Midwest
PJM Interconnection
DTrending down
FERC extends RBP briefs to Jan 11. No 205 yet. Still suspended to Feb 28.
Western United States
Western Electricity Coordinating Council
C+Holding
Board still Oct 28; 205 planned Nov 16. No tariff or time-to-power move.
On the calendar
WECC
CAISO Board decision on large-load enhancements
Passed · read in next update
PJM
Revised RBP 205 filing window closes
Passed · read in next update
WECC
CAISO and PTO section 205 filings
MISO
Date requested in ER26-3650
ERCOT
Statewide audit; the energization freeze binds until then
PJM
EL26-108 initial briefs now due
PJM
EL26-108 reply briefs now due
PJM
RBP suspension ends; effective date
Pending
SPP
FERC order on ER26-3685
Pending
PJM
RBP paper hearing or revised 205
How This Is Scored
The HD Market Scorecard is Hyperscape Digital's own weekly assessment of how hospitable each major US market is to new large-load interconnection — an opinion index built from public data and our on-the-ground read, not a third-party rating. Grades run A through F on the weighted factors below.
| Factor | Weight | Sources |
|---|---|---|
| Interconnection queue wait / time-to-power | 35% | LBNL Queued Up, ISO queue data |
| Uncommitted capacity / reserve margin | 25% | ISO reports, NERC |
| Large-load tariff & moratorium climate | 20% | Regulatory filings, news |
| Forward power price / congestion | 10% | ISO market data |
| HD on-the-ground read | 10% | Hyperscape Digital |
Grade History
Every published change to the index, most recent first. Grades held since July 16, 2026 are unchanged from inception.
August 17, 2026
ERCOTAA-
Texas paused the Batch Zero large-load interconnection study pending a statewide data-center audit, degrading time-to-power (35%) and tariff/moratorium climate (20%). Held to one notch: the pause is finite, ERCOT retains the deepest uncommitted capacity and lowest forward prices on the board, and the audit favors self-generation structures.
Read the brief →
Citing the Scorecard
The HD Market Scorecard is Hyperscape Digital’s own opinion index, not a third-party rating. Quote it freely with attribution:
HD Market Scorecard, Hyperscape Digital, October 26, 2026. hyperscapedigital.com/scorecard