HD Market Scorecard · Texas
ERCOT Large-Load Interconnection Grade
Electric Reliability Council of Texas · As of October 26, 2026
ERCOT is the default US market for speed-to-power. It still has the deepest uncommitted capacity and the lowest forward prices on this board. What it no longer has, as of August 2026, is a frictionless energization gate for new data-center and crypto load at or above 75 MW.
On June 18, 2026 the Public Utility Commission of Texas approved ERCOT's Batch Zero process: large-load requests of 75 MW and above are studied in a cohort rather than one at a time. The queue behind that process later printed at roughly 474 GW of interconnection requests, about 90% of it data centers — more than five times ERCOT's record peak. Classification notices were due August 7.
What the grade is pricing
Powered land with executed interconnection standing, clean attestations, or a behind-the-meter path is the scarce asset. Unvetted queue position is not. Senate Bill 6 sits underneath the audit: Texas is writing the right to curtail co-located large load under stress, and the PUCT has already held that curtailment is not capped by the paired generator's capacity.
ERCOT remains the highest grade on this board. It is no longer the market where time-to-power can be treated as a given.
ERCOT
A-
Trending down
TCEQ letter Oct 19; STEERS down. Freeze still binds to Dec 10.
Opinion index · not a third-party rating
Why the grade moved
Governor Abbott's August 3 data-center audit stopped that clock. ERCOT skipped the August 7 classifications, then said it would not authorize ≥75 MW computational load to energize until it finishes a project-by-project verification of MW, site control, financial security, and ownership. It has aimed the audit at December 10. The long-term load and reliability study that had targeted April 9, 2027 is slipping.
The HD Market Scorecard cut ERCOT from A to A- on August 17, on time-to-power (35%) and large-load tariff/moratorium climate (20%). It held there through the December clock and the energization freeze. One notch per shock: the pause is finite, grandfathered load still energizes, and Texas still clears bring-your-own-power deals. An A would imply a gate that no longer exists.
Full board, weights, and citation format: HD Market Scorecard. How the 35/25/20/10/10 weights work: methodology.
Grade History
Published changes to ERCOT, most recent first. Grades held since July 16, 2026 are unchanged from inception.
August 17, 2026
ERCOTAA-
Texas paused the Batch Zero large-load interconnection study pending a statewide data-center audit, degrading time-to-power (35%) and tariff/moratorium climate (20%). Held to one notch: the pause is finite, ERCOT retains the deepest uncommitted capacity and lowest forward prices on the board, and the audit favors self-generation structures.
Read the brief →
Explainers
ERCOT Batch Zero: the ≥75 MW Large-Load Interconnection Process
What ERCOT Batch Zero is, why August classifications were delayed, what the September verification and community-impact RFIs mean, why the September 21 TCEQ permit pause and the October 19 compliance letter sit on the same audit, and why energization still waits on the December 10 audit.
Texas Senate Bill 6: Large-Load Interconnection and Curtailment
How Texas Senate Bill 6 governs ≥75 MW large loads in ERCOT, what the PUCT adopted in §25.194, and why that sits next to the Batch Zero audit.
Time-to-Power: the 35% Factor on the HD Market Scorecard
What time-to-power means for a new data-center large load, why it is 35% of Hyperscape Digital's market grade, and how ERCOT, PJM, SPP, MISO, and WECC currently differ.
Related briefs
October 26, 2026
TCEQ Writes Abbott. STEERS Goes Offline
September 28, 2026
Abbott Directs TCEQ to Halt Data Center Permits. Energization Stays Frozen
September 21, 2026
ERCOT Issues the Community-Impact RFI. The Large-Load Rule Is Filed
September 14, 2026
ERCOT Starts the Batch Zero Paper Clock. Energization Still Frozen
September 8, 2026
ERCOT Issues Conditional Batch Zero Classifications. Energization Stays Frozen
September 1, 2026
The Energization Gate Closed: State of the AI & Hyperscale Data Center Market — August 2026
August 31, 2026
ERCOT Freezes Large-Load Energization as the Batch Zero Audit Bites
August 24, 2026
ERCOT Puts a December Clock on Texas Time-to-Power
August 17, 2026
Texas Pulls the Brake: ERCOT Freezes a 474 GW Data-Center Queue for a Statewide Audit
