# ERCOT Starts the Second-Round Batch Zero RFIs. Energization Still Frozen

HD Intelligence Desk · Brief · November 9, 2026

## What Happened

On November 4, 2026, ERCOT filed in Public Utility Commission of Texas Project No. 59142, Item 78, for the November 5 open meeting, agenda item 38, and Attachment A says transmission providers timely returned every first-round Batch Zero verification response, from 257 developers and about 5,140 questions, and that ERCOT is issuing second-round requests to an expected 80 percent of those developers, with fewer questions and a five-business-day deadline under Planning Guide Section 9.1(8). The review is not finished, and the gaps already recurring are affiliate documentation, site control, long-lead equipment ordered for delivery before energization, and the amount of financial security posted. Attachment B, marked preliminary as of November 5 and subject to change, says the State and Community Impact request went to 465 loads, 433 responded, covering about 177 GW and about 97 percent of requested interconnection capacity, all 245 loads of 75 MW or greater responded and account for about 166 GW, and the final report is still targeted for December 10, 2026. The November 4 cover letter says the developer good-cause requests ERCOT will pursue are more time to post financial security under Planning Guide Revision Request 145, which those loads have now posted, and more time for a late Form W on provisional controllable-load status, and that a further request, for loads submitted as energized under Planning Guide Section 9.2.1.1(1)(b) that had not energized by July 10, 2026, was expected the week of November 9 for the December 17 open meeting.

## Why It Matters

We hold ERCOT at A-. Time-to-power is 35% of the grade, and the second-round verification requests and the community-impact tally are the December 10 audit, not a thaw and not a second freeze. Market Notice M-B091426-01 still expects that report by December 10 and restates the August 3 directive holding advancement through interconnection until the review is done. Trend stays down, and the same shock is not cut twice.

## The rest of the board

PJM's ER27-330 docket sheet from November 3 through November 9 shows doc-less motions to intervene and no Commission order. The ER26-3515 sheet from October 9 through November 9 shows the October 9 order and the Pennsylvania Public Utility Commission's October 15 service-list filing, accession 20261015-5085, and no compliance filing on the Large Load definition and the registry. Order 197 FERC ¶ 61,019 required that filing within 30 days. We hold PJM at D. The 2027/2028 Base Residual Auction cleared 6,623 MW short of the reliability requirement, and the 2028/2029 auction cleared 6,831 MW short. Order 196 FERC ¶ 61,245 still suspends Reliability Backstop Procurement to February 28, 2027, subject to refund. Trend stays down. The same shock is not cut twice. MISO's ER26-3650 docket sheet shows a November 3 answer by the Data Center Coalition, accession 20261103-5190, and no order. That is process, not reserve margin. We hold MISO at C.

## Sources

1. [ERCOT updates, Batch Zero verification, community-impact RFI, and medium load, Project No. 59142, Item 78, ERCOT, filed Nov 4 2026](https://interchange.puc.texas.gov/Documents/59142_78_1699635.PDF)
2. [Open Meeting Agenda, Project No. 59142, item 38, Public Utility Commission of Texas, Nov 5 2026](https://ftp.puc.texas.gov/public/puct-info/agency/om/110526Final.pdf)
3. [ERCOT Market Notice M-B091426-01: State and Community Impact RFI, report expected by Dec 10, Sep 14 2026](https://www.ercot.com/services/comm/mkt_notices/M-B091426-01)
4. [Docket sheet, ER27-330, filed Oct 29–Nov 9 2026, FERC eLibrary](https://elibrary.ferc.gov/eLibrary/docketsheet?docket_number=er27-330&sub_docket=all&dt_from=2026-10-29&dt_to=2026-11-09&date_type=filed_date&date_range=custom&chklegadata=false)
5. [Docket sheet, ER26-3515, filed Oct 9–Nov 9 2026, FERC eLibrary](https://elibrary.ferc.gov/eLibrary/docketsheet?docket_number=er26-3515&sub_docket=all&dt_from=2026-10-09&dt_to=2026-11-09&date_type=filed_date&date_range=custom&chklegadata=false)
6. [Order Accepting Tariff Revisions in Part and Rejecting Tariff Revisions in Part, 197 FERC ¶ 61,019, FERC, Oct 9 2026](https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9207/20261009-er26-3515-000.pdf)
7. [Order Accepting Reliability Backstop Procurement and Establishing Further Procedures, 196 FERC ¶ 61,245, FERC, Sep 29 2026](https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9154/20260929-er26-3380-000.pdf)
8. [Docket sheet, ER26-3650-000, filed Oct 19–Nov 9 2026, FERC eLibrary](https://elibrary.ferc.gov/eLibrary/docketsheet?docket_number=er26-3650&sub_docket=000&dt_from=2026-10-19&dt_to=2026-11-09&date_type=filed_date&date_range=custom&chklegadata=false)

HTML: https://hyperscapedigital.com/news/ercot-starts-second-round-batch-zero-rfis