# CAISO Files the Large-Load Tariff. Interim Service Waits on an Order

HD Intelligence Desk · Brief · November 23, 2026

## What Happened

On November 16, 2026, the California ISO filed Docket No. ER27-532-000, accession 20261116-5343, which eLibrary describes as a resubmission under a different filing code, filing type 10, defining a Large Load as an end user at a single site behind one or more points of interconnection to the CAISO-controlled grid with a peak load of 50 MW or greater, adding Flexible Interim Load Interconnection service that lets the load interconnect before its network upgrades or interconnection facilities are complete and then take firm service, and asking for an effective date of February 16, 2027, with scheduling-coordinator sections 25.7.3 and 25.7.3.1 effective November 1, 2027, and settlements section 11.36 effective April 30, 2028. The same amendment was first noticed as Docket No. ER27-506-000, accession 20261116-5179, described as a compliance filing with comments due at 5 p.m. Eastern Time on December 7, 2026. On November 18 the ISO filed accession 20261118-5181, an amendment in that docket, filing type 80, and accession 20261118-5188, a withdrawal of the entire proceeding, filing type 90. The Commission's combined notice dated November 18 sets comments on ER27-532-000 at 5 p.m. Eastern Time on December 16, 2026, and on the November 18 amendment at 5 p.m. Eastern Time on December 9, and the ER27-532 docket sheet from November 16 through November 23 shows the resubmission, that notice, doc-less motions to intervene, and no Commission order.

## Why It Matters

We hold WECC at C+. Time-to-power is 35% of the grade. Flexible Interim Load Interconnection is service before the upgrades, and the filed tariff keeps continuous operation from 58.8 Hz through 61.2 Hz and a 20 MW per minute cap on the average ramp over a rolling ten-minute interval. A load that is already operating, or that has a complete request with the participating transmission owner before February 16, 2027, stays outside the new rules unless it later modifies or increases. The November 16 combined notice also lists Pacific Gas and Electric Docket No. ER27-513-000, accession 20261116-5257, and describes Docket No. ER27-508-000, accession 20261116-5210, as SCE large-load transmission-owner tariff revisions, each effective February 16, 2027. Docket No. ER27-532-000 is a filing, not an accepted service. Trend stays flat. The same shock is not cut twice.

## The rest of the board

On November 16, PJM filed Docket No. ER27-531-000, accession 20261116-5340, a Fast Energization Process that studies generation interconnection requests and transmission service for large loads in one 12-month process, with Part III, new Part XI service for Interim Network Integration Transmission Service, Firm Contract Demand, and Non-Firm Contract Demand, and part of Part VIII effective March 16, 2027, and an indefinite effective date for the Fast Energization provisions until Cycle 01 passes Decision Point II. The transmittal expects that submission window to open in late November 2027 and the first cycle to finish in 2029. The November 18 combined notice sets comments at 5 p.m. Eastern Time on January 15, 2027. The docket sheet through November 23 shows doc-less interventions and no Commission order. The same day PJM filed Docket No. ER27-522-000, accession 20261116-5309, operational requirements for large computational load and annual reporting, effective January 16, 2027, with comments due December 7. The November 16 notice lists Docket No. ER27-520-000, accession 20261116-5300, under PECO Energy Company, described as PJM transmission-owner tariff revisions for service to co-located loads and large loads, effective March 16, 2027, comments December 7. We hold PJM at D. The 2027/2028 Base Residual Auction cleared 6,623 MW short of the reliability requirement, and the 2028/2029 auction cleared 6,831 MW short. Order 196 FERC ¶ 61,245 still suspends Reliability Backstop Procurement to February 28, 2027, subject to refund. Comments on ER27-454-000 are still due November 30. Trend stays down. The same shock is not cut twice. On November 16 MISO filed Docket No. ER27-526-000, accession 20261116-5323, a large-load review, cost-recovery, and transmission-services filing effective February 14, 2027, with comments due December 16, and Docket No. ER27-527-000, accession 20261116-5326, Grid Responsive Integration Transmission Service effective March 16, 2027, with comments due December 7. The ER27-526 sheet through November 23 shows interventions, a November 18 motion for a 30-day extension of time to comment, accession 20261118-5011, and no order. That is process, not reserve margin. We hold MISO at C. On November 18 SPP filed Docket No. ER27-559-000, accession 20261118-5252, to enhance transmission service for High Impact Large Loads and non-transmission facilities, effective February 16, 2027. On November 19 it filed Docket No. ER27-577-000, accession 20261119-5227, to establish a Load Safe Harbor Limit for delivery-point costs, effective February 17, 2027, and Docket No. ER27-578-000, accession 20261119-5243, to add Price Adaptive Load Service, with the effective date left open and recorded as December 31, 9998. The ER26-3685 docket sheet from November 1 through November 23 shows no filings. There is no order on the Conditional High Impact Large Load clarification. We hold SPP at B+. Trend stays flat.

## Sources

1. [Large Loads Tariff Amendment, Docket No. ER27-532-000, California ISO, filed Nov 16 2026](https://www.caiso.com/documents/nov-16-2026-tariff-amendment-large-loads-er27-532.pdf)
2. [eLibrary accession 20261116-5343, Large Load Tariff Amendment resubmission, Docket No. ER27-532-000, California ISO, filed Nov 16 2026](https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261116-5343&optimized=false)
3. [Combined Notice of Filings #1, accession 20261116-5179 noticed as ER27-506-000, FERC, dated Nov 16 2026](https://www.federalregister.gov/documents/2026/11/19/2026-23607/combined-notice-of-filings-1)
4. [Combined Notice of Filings #1, accession 20261118-3090, FERC, dated Nov 18 2026](https://www.federalregister.gov/documents/2026/11/23/2026-23765/combined-notice-of-filings-1)
5. [eLibrary accession 20261118-5181, Amendment to the Large Load Amendment, Docket No. ER27-506, California ISO, filed Nov 18 2026](https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261118-5181&optimized=false)
6. [eLibrary accession 20261118-5188, Withdrawal of the Large Load Amendment proceeding, Docket No. ER27-506, California ISO, filed Nov 18 2026](https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20261118-5188&optimized=false)
7. [Docket sheet, ER27-532, filed Nov 16–23 2026, FERC eLibrary](https://elibrary.ferc.gov/eLibrary/docketsheet?docket_number=er27-532&sub_docket=all&dt_from=2026-11-16&dt_to=2026-11-23&date_type=filed_date&date_range=custom&chklegadata=false)
8. [Proposed Tariff Revisions for Large Loads and Compliance with EL26-67, Docket No. ER27-531-000, PJM, filed Nov 16 2026](https://www.pjm.com/-/media/DotCom/documents/ferc/filings/2026/20261116-er27-531-000.pdf)
9. [Docket sheet, ER27-531, filed Nov 16–23 2026, FERC eLibrary](https://elibrary.ferc.gov/eLibrary/docketsheet?docket_number=er27-531&sub_docket=all&dt_from=2026-11-16&dt_to=2026-11-23&date_type=filed_date&date_range=custom&chklegadata=false)
10. [Order Accepting Reliability Backstop Procurement and Establishing Further Procedures, 196 FERC ¶ 61,245, FERC, Sep 29 2026](https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9154/20260929-er26-3380-000.pdf)
11. [Docket sheet, ER27-526, filed Nov 16–23 2026, FERC eLibrary](https://elibrary.ferc.gov/eLibrary/docketsheet?docket_number=er27-526&sub_docket=000&dt_from=2026-11-16&dt_to=2026-11-23&date_type=filed_date&date_range=custom&chklegadata=false)
12. [eLibrary accession 20261118-5252, Transmission service for HILLs and non-transmission facilities, Docket No. ER27-559-000, Southwest Power Pool, filed Nov 18 2026](https://elibrary.ferc.gov/eLibrary/docinfo?accession_Number=20261118-5252)
13. [eLibrary accession 20261119-5227, Load Safe Harbor Limit for delivery-point costs, Docket No. ER27-577-000, Southwest Power Pool, filed Nov 19 2026](https://elibrary.ferc.gov/eLibrary/docinfo?accession_Number=20261119-5227)
14. [eLibrary accession 20261119-5243, Price Adaptive Load Service, Docket No. ER27-578-000, Southwest Power Pool, filed Nov 19 2026](https://elibrary.ferc.gov/eLibrary/docinfo?accession_Number=20261119-5243)
15. [Docket sheet, ER26-3685, filed Nov 1–23 2026, FERC eLibrary](https://elibrary.ferc.gov/eLibrary/docketsheet?docket_number=er26-3685&sub_docket=all&dt_from=2026-11-01&dt_to=2026-11-23&date_type=filed_date&date_range=custom&chklegadata=false)